Skip to main content

Redevelopment

Back

Ash Street Demand-Led Redevelopment Project (DL-11:YTM)

Location
Nos. 5-13 (odd numbers only) Ash Street, Tai Kok Tsui
Area
About 474 square metres
Affected buildings
5 street numbers of buildings
Affected population
About 234
Affected property interests
About 78
Affected households
About 67
Project photo
Project photo

Project Development Information


Total GFA About 3,522 square metres
Residential Flats About 69
Commercial GFA About 391 square metres

Project Status


The project was commenced on 29 May 2015. 

No objection to the project was received by the URA during the two-month publication period (29 May to 29 July 2015).  

SDEV has considered the project and authorized the URA to proceed with the project on 11 January 2016.

Acquisition in progress.

Project Programme


Targeted completion by 2021/2022.

More Information


The project is implemented is accordance with the "Urban Renewal Strategy" ("URS") (2011) which includes the flat-for-flat options an alternative option to cash compensation to domestic owner-occupiers.  They can consider cash compensation or using it to buy a new flat-for-flat in-situ in the new development or in the same district or in Kai Tak development.

Back