Hang On Street Project (Demand-led Redevelopment Project (DL-10:KT))

Location
Nos. 12-30 Hang On Street (even numbers) , Kwun Tong
Area
About 865 square meters
Affected buildings
10 street numbers
Affected population
About 393
Affected property interests
About 90
Affected households
About 151

Project Development Information


Total GFA About 6,663 square meters
Residential Flats About 138 units
Non-Domestic GFA About 741 square meters (including 500 square meters for Government, Institution or Community use)

Project Status


The Project was commenced on 7 November 2014.

The URA received objections and comment to the project during the two-month publication period (from 7 November 2014 to 7 January 2015).

SDEV has considered the project and the related information and authorized the URA to proceed with the project without any amendment on 7 July 2015.  The SDEV's decision was published in the Gazette on 17 July 2015.

Construction works in progress.

Project Programme


Targeted Completion by 2021/2022.

More information


The projected is implemented is accordance with the Urban Renewal Strategy (2011) which includes the flat-for flat options to be offered as an alternative options to cash compensate to domestic owner-occupiers.  They can consider cash compensation or using it to buy a new flat-for-flat in- situ in the new development or in the same district or in Kai Tak Development.