777-783 Yu Chau West Street Industrial Building Redevelopment Pilot Scheme Project (IB-2:SSP)
- Location
- Nos. 777-783 Yu Chau West Street, Cheung Sha Wan
- Area
- About 1,393 square meters
- Affected buildings
- 1
- Affected property interests
- 40
- Affected operators
- About 40
Project Development Information
Commercial GFA | About 16,700 square meters |
Project Progress
The project was commenced and published in the Gazette on 18 January 2013.
Three objections to the project were received by the URA during the two-month publication period (18 January to 18 March 2013).
The Secretary for Development (SDEV) has authorized the Urban Renewal Authority (URA) to proceed with the Project. The authorization was given under section 24(4)(a) of the Urban Renewal Authority Ordinance (URAO) and was published in the Government Gazette on 30 August 2013.
The URA submitted a s.16 Planning Application to the Town Planning Board (TPB) for a proposed Shop and Services (Neighbourhood Resources Centre) on 13 August 2018. This planning application was approved with conditions by the TPB on 19 October 2018.
Project Programme
Project commenced in January 2013
Targeted completion by 2020/2021